The Broadway Subway is a 5.7 km extension of the Millennium Line from VCC-Clark Station to Broadway and Arbutus, with six underground stations. The BC government says the project remains on schedule to open in fall 2027 and costs nearly $3 billion.
| Fact | Value |
|---|---|
| Route | VCC-Clark Station to Broadway and Arbutus Street |
| Length | 5.7 km |
| Structure | 700 metres elevated guideway, 5 km of tunnels |
| New stations | 6 underground stations |
| West end | Arbutus Street, an interim terminus |
| Scheduled opening | Fall 2027 |
| Travel time, VCC-Clark to Arbutus | 11 minutes |
| Total cost | Nearly $3 billion |
| Opening-day capacity | Three times the current 99 B-Line |
Updated November 21, 2026, using the BC government’s September 2026 progress release and TransLink’s project pages.
Route and the six stations of the extension
The Millennium Line extension continues from VCC-Clark Station on 700 metres of elevated guideway, then runs underground along Broadway for 5 km. TransLink lists six new underground stations on its Broadway Subway project page. TransLink confirmed the final names in 2020, from east to west.
| Station | Planned location | Connection |
|---|---|---|
| Great Northern Way-Emily Carr | Thornton Street, east side, just north of Great Northern Way | Emily Carr University campus, Central Valley Greenway, bike parkade |
| Mount Pleasant | Broadway at Main Street, southwest corner | Mount Pleasant shops and housing |
| Broadway-City Hall | Reuses the Canada Line entrance at Broadway and Cambie Street, southeast corner | Underground link to the Canada Line |
| Oak-VGH | Broadway at Laurel Street, southwest corner, near Oak Street | Vancouver General Hospital and the medical district |
| South Granville | Broadway at Granville Street, northeast corner | Serves South Granville, Burrard Slopes and Granville Island |
| Arbutus | Broadway at Arbutus Street, northeast corner, plus a bus loop | 99 B-Line to UBC, Arbutus Greenway, bike parkade |
Locations come from a 2019 BC government station release. Final names come from TransLink’s September 2020 naming announcement.
Opening date and the interim terminus at Arbutus
The BC government’s September 2026 progress release says the Broadway Subway remains on schedule to open for passenger service in fall 2027. All trackwork was due to finish that week. TransLink’s project page gives the same year, 2027, and neither source names a single opening day.
Arbutus Street is the interim terminus, so Millennium Line trains stop there for now. B-Line buses cover Arbutus Street to UBC until a possible future UBC extension, TransLink says.
Travel time and capacity on the new line
The trip from VCC-Clark Station to Arbutus Station will take 11 minutes once the line opens, according to the BC government. The same release says the average transit commuter will save almost 30 minutes a day. On opening day, the line will carry three times the capacity of the current 99 B-Line.
Broadway already carries more than 100,000 transit trips a day, and TransLink calls it the busiest bus route in Canada and the U.S. The Broadway Subway project website repeats the 11-minute figure.
Cost of the Broadway Subway and who pays
The Broadway Subway costs nearly $3 billion in total, according to the BC government’s progress release. The Government of Canada contributes nearly $897 million, and the Government of BC nearly $2 billion. The City of Vancouver contributes $100.3 million.
- Government of Canada: nearly $897 million
- Government of BC: nearly $2 billion
- City of Vancouver: $100.3 million
Construction on Broadway until the line opens
Vehicles have been barred from two blocks of West Broadway, from Alberta Street to Cambie Street, since July 2026. Buses and cars detour along 8th Avenue, where bus-priority measures aim to limit delays. People on foot still reach businesses, services and homes, and Broadway is expected to fully reopen to vehicles in January 2027.
Crews finished removing the traffic deck at Broadway-City Hall Station in August 2026, and utilities, backfilling and street restoration come next. At Mount Pleasant Station, East Broadway carries all driving lanes again, with widened sidewalks, from Main to Quebec.
The Broadway Subway team runs a 24/7 Construction Information Line at 1-844-815-6114, listed on the Broadway Subway stations and project page.
What the Broadway Subway means for riders
Riders on the Broadway corridor will switch from the 99 B-Line to the Millennium Line for the trip to Arbutus. Broadway-City Hall links the Millennium Line directly to the Canada Line underground. Access runs from the Millennium Line fare gates and both Canada Line platforms. UBC riders will still finish the trip on the 99 B-Line from Arbutus.
Until the opening, buses keep running through the work zone. Since July 16, 2026, TransLink has moved some stops near Broadway and Cambie.
- Eastbound routes 9, 99 and N9: stop 60535, on Broadway south side, Cambie to Ash
- Westbound route 9: stop 58269, on Broadway north side, Cambie to Ash
- Northbound routes 15, 17 and N15: stop 60676, on Cambie east side, 10th to 11th avenues
Check TransLink’s Broadway stop changes and alerts page before travelling.
What stays on buses before and after opening
Before the opening, the 99 B-Line and other Broadway buses remain the way to travel the corridor. After the opening, B-Line service continues between Arbutus Street and UBC, so the westbound trip to UBC still uses a bus. TransLink describes a Millennium Line extension to UBC only as possible and unscheduled.
Where the facts on this page come from
- BC government progress release, September 2026: route, cost, funding, travel time, schedule and Broadway closure.
- TransLink Broadway Subway project page and Broadway Buzz page: stations, interim terminus and stop changes.
- Broadway Subway project website: route length, Canada Line connection and contact lines.
- TransLink Buzzer (2020) and BC government release (2019): station names and locations.