The Pattullo Bridge replacement is the stal̕əw̓asəm (Riverview) Bridge, and all four of its lanes opened to vehicles on Saturday, Feb. 14, 2026. The BC government lists the project at $1.637 billion, and removing the old Pattullo Bridge takes about two years.
| Fact | Value |
|---|---|
| Official name | stal̕əw̓asəm Bridge; English name Riverview |
| Connects | New Westminster and Surrey, across the Fraser River |
| Four lanes open to vehicles | Saturday, Feb. 14, 2026 |
| Lanes | Four wider lanes with a centre median |
| Walking and cycling | Barrier-separated lanes on both sides |
| Toll | None; the bridge is toll-free |
| Length | 1,235 metres, single-tower cable-stay design |
| Project cost | $1.637 billion (earlier budget: $1.377 billion) |
| Old Pattullo Bridge | Removal began February 2026 and takes about two years |
Updated November 21, 2026, using BC government news releases and the Province’s project page.
Opening date and how traffic moved across
The stal̕əw̓asəm Bridge opened to vehicles on Saturday, Feb. 14, 2026, according to the full-opening release from the Ministry of Transportation. The move came in stages.
A closure notice for both bridges shut them from 8 p.m. on Friday, February 6 for about one week. Crews connected the roads on each side.
The new bridge then reopened with three lanes, two northbound and one southbound.
Traffic shifted fully to the new bridge in late February.
The original schedule was far earlier. An April 2021 progress update had already moved the opening from late 2023 into 2024, and the bridge finally opened in 2026.
Lanes, walking paths and cycling paths
The stal̕əw̓asəm Bridge has four wider lanes with a centre median barrier. The Province’s Pattullo Bridge project page says walking and cycling lanes run on both sides of the bridge, separated from traffic by a barrier. Drivers pay no toll.
Path connections were still being built at opening. Access for people on foot and bikes was due through the east-side multi-use path in spring 2026.
The old Pattullo Bridge sidewalk stayed open to walkers and cyclists during the one-week closure.
The 2021 update described four lanes with capacity to expand to six. The 2026 releases do not mention six lanes, so treat that as a long-term option.
Cost of the new bridge and who pays
The Province’s project page puts the stal̕əw̓asəm Bridge at $1.637 billion. Transportation Investment Corporation, a provincial Crown corporation, delivers the project. Fraser Crossing Partners holds the design-build contract, and the Province will own and maintain the bridge.
The cost is higher than the $1.377 billion in a 2019 BC government release.
The 2019 figure was the approved budget for the full job, including removal of the existing bridge and interest during construction. The gap between the two published totals is $260 million.
What happens to the old Pattullo Bridge
Deconstruction of the old Pattullo Bridge began in February 2026, once the new bridge was fully open. Removal will take approximately two years, says the Province. Crews had moved equipment in for preparatory work before concrete and steel removal.
The Province says demolition is needed to finish the Columbia Street on-ramp, the Highway 17 off-ramp and some multi-use path connections.
Two years from February 2026 points to early 2028, but the release gives a duration, not a completion date.
Connections for drivers on both sides
The new bridge links Surrey and New Westminster and, in the Province’s words, serves local and national goods movement. Ramps arrive in stages. On the first day of the shift, one northbound lane exited to East Columbia by a new off-ramp, per a late-2025 naming and traffic-shift release.
- Royal Avenue on-ramp: one southbound lane of the old bridge stayed open in February so crews could finish this connection.
- Columbia Street on-ramp: finishing it depends on removing the old bridge.
- Highway 17 off-ramp: finishing it depends on removing the old bridge.
Check road conditions on DriveBC before you head out. The project also runs a 24-hour construction information line at 1-844-815-6149.
Open questions the BC government has not settled
The BC government releases give a two-year duration for demolition but no completion date. They say spring 2026 was the plan for the east-side path, without a confirmed opening day. The six-lane expansion has no date. Walkers and cyclists should check the project site, linked from the Province’s releases, for path closures before relying on a route.
The name stal̕əw̓asəm and its meaning
Kwantlen First Nation and Musqueam Indian Band chose the name stal̕əw̓asəm for the bridge. The Province reads it as roughly a place to see the river, and Riverview is the English name. Road signs show both the hən̓q̓əmin̓əm̓ name and the English translation. Coast Salish artwork is being added to the bridge and its surroundings, and the name appears on the crossbeam.
Where the facts on this page come from
- BC government full-opening release: opening date, design, path plans, demolition and size.
- BC government closure notice: closure, lane counts after reopening.
- BC government naming release, late 2025: name, meaning and first traffic shift.
- Province project page: $1.637 billion cost, bridge features, construction line.
- BC government releases, 2019 and 2021: earlier $1.377 billion budget, delay and six-lane capacity.